Cost Overruns in Hydrocarbon Megaprojects: A Critical Review and Implications for Research

Article


Olaniran, Olugbenga Jide, Love, Peter E. D, Edwards, David, Olatunji, Oluwole Alfred and Matthews, Jane. 2015. "Cost Overruns in Hydrocarbon Megaprojects: A Critical Review and Implications for Research." Project Management Journal. 46 (6), pp. 126-138. https://doi.org/10.1002/pmj.21556
Article Title

Cost Overruns in Hydrocarbon Megaprojects: A Critical Review and Implications for Research

ERA Journal ID19374
Article CategoryArticle
AuthorsOlaniran, Olugbenga Jide (Author), Love, Peter E. D (Author), Edwards, David (Author), Olatunji, Oluwole Alfred (Author) and Matthews, Jane (Author)
Journal TitleProject Management Journal
Journal Citation46 (6), pp. 126-138
Number of Pages13
Year2015
Place of PublicationUnited States
ISSN1938-9507
8756-9728
Digital Object Identifier (DOI)https://doi.org/10.1002/pmj.21556
Web Address (URL)https://journals.sagepub.com/doi/10.1002/pmj.21556
Abstract

Cost overruns are prevalent in hydrocarbon (oil and gas) megaprojects. A recent report indicates that 64% of ongoing megaprojects globally are facing cost overruns. Despite their increasing occurrence, there has been limited published research in the mainstream literature that has specifically examined why and how they occur. Consequently, suggestions regarding how to constructively address cost overruns in hydrocarbon megaprojects are scant. To better understand the causal nature of cost overruns in hydrocarbon megaprojects, this article provides a critical review of the extant literature. Findings from the research indicate that complex interactions between project characteristics, people, technology, and structure and culture contribute to cost overruns occurring. As a result, it is suggested that chaos theory can be used to explain how cost overruns arise in hydrocarbon megaprojects. This article provides a reference point for engendering future research in this pervasive and fertile area.

Keywordscost overrun; hydrocarbon; learning; megaprojects; research
ANZSRC Field of Research 2020330299. Building not elsewhere classified
330207. Quantity surveying
330203. Building industry studies
Public Notes

Files associated with this item cannot be displayed due to copyright restrictions.

Byline AffiliationsCurtin University
Birmingham City University, United Kingdom
Institution of OriginUniversity of Southern Queensland
Permalink -

https://research.usq.edu.au/item/q73zz/cost-overruns-in-hydrocarbon-megaprojects-a-critical-review-and-implications-for-research

  • 167
    total views
  • 2
    total downloads
  • 8
    views this month
  • 0
    downloads this month

Export as

Related outputs

Modular Construction as a Sustainable Eco-Friendly Building Solution
Qureshi, Hisham Jahangir, Ullah, Fahim and Olatunji, Oluwole. 2025. "Modular Construction as a Sustainable Eco-Friendly Building Solution." Farsangi, Ehsan Noroozinejad, Rasouli, Aso Haji, Dawood, Nashwan and Morrison, Greg (ed.) Construction Applications of Virtual Reality, Volume 3. Singapore. Springer. pp. 13-47
Curbing the Spread of Communicable Diseases in Residential Aged Care Facilities Through Design Considerations
Tanveer, Rameesha, Qayyum, Siddra, Ullah, Fahim and Olatunji, Oluwole. 2025. "Curbing the Spread of Communicable Diseases in Residential Aged Care Facilities Through Design Considerations." Farsangi, Ehsan Noroozinejad, Rasouli, Aso Haji, Dawood, Nashwan and Morrison, Greg (ed.) Construction Applications of Virtual Reality, Volume 2. Singapore. Springer. pp. 53-69
Project attributes influencing contractors' bid decision
Olatunji, Oluwole, Ramanayaka, Chamil and Ullah, Fahim. 2025. "Project attributes influencing contractors' bid decision." Built Environment Project and Asset Management. https://doi.org/10.1108/BEPAM-11-2024-0272
Role of Ventilation and Spatial Designs in Airborne Disease Transmission Within Residential Aged-Care Facilities
Ullah, Fahim, Olatunji, Oluwole, Qayyum, Siddra and Tanveer, Rameesha. 2025. "Role of Ventilation and Spatial Designs in Airborne Disease Transmission Within Residential Aged-Care Facilities." Designs. 9 (5). https://doi.org/10.3390/designs9050110
A cost-benefit analysis of construction safety implementation in developing countries
Khan, Shamraiza, Thaheem, Muhammad Jamaluddin, Akram, Ramsha, Ullah, Fahim, Nasir, Abdur Rehman and Olatunji, Oluwole. 2025. "A cost-benefit analysis of construction safety implementation in developing countries." Umeokafor, Nnedinma, Emuze, Fidelis, Izam, Che Khairil, Sunindijo, Riza Yosia, Umar, Tariq, Windapo, Abimbola and Teizer, Jochen (ed.) Handbook of Drivers of Continuous Improvement in Construction Health, Safety, and Wellbeing. United Kingdom. Routledge. pp. 189-206
The relationship between labour-only procurement and health and safety performance of construction projects
Umeokafor, Nnedinma, Windapo, Abimbola and Olatunji, Oluwole Alfred. 2024. "The relationship between labour-only procurement and health and safety performance of construction projects." International Journal of Productivity and Performance Management. 73 (7), pp. 2156-2182. https://doi.org/10.1108/IJPPM-09-2022-0490
Guest editorial: Construction industry as net-zero enabler: driving circular economy and sustainability through innovation/change management
Ramanayaka, Chamil Erik, Olatunji, Oluwole Alfred, Rahnamayiezekavat, Payam and Siriwardana, Chandana. 2024. "Guest editorial: Construction industry as net-zero enabler: driving circular economy and sustainability through innovation/change management." Built Environment Project and Asset Management. 14 (5), pp. 677-681. https://doi.org/10.1108/BEPAM-09-2024-249
Causal relationship between project financing and overruns in major dam projects in Africa
Olatunji, Oluwole Alfred, Rotimi, James Olabode Bamidele, Rotimi, Funmilayo Ebu and Silva, Chathurani C.W.. 2024. "Causal relationship between project financing and overruns in major dam projects in Africa." Engineering, Construction and Architectural Management. https://doi.org/10.1108/ECAM-03-2023-0286
Understanding the impact of urban heat islands on crime: insights from temperature, population density, and green canopy cover
Jonescu, Emil E., Ramanayaka, Chamil Erik, Olatunji, Oluwole A. and Uylaki, Talia J.. 2024. "Understanding the impact of urban heat islands on crime: insights from temperature, population density, and green canopy cover." Crime Science. 13 (1). https://doi.org/10.1186/s40163-024-00214-w
A scoping review of green Internet of Things in construction and smart cities: current applications, adoption strategies and future directions
Ullah, Fahim, Olatunji, Oluwole and Qayyum, Siddra. 2024. "A scoping review of green Internet of Things in construction and smart cities: current applications, adoption strategies and future directions." Smart and Sustainable Built Environment. https://doi.org/10.1108/SASBE-11-2023-0349
Post-Construction Defects in Multi-Unit Australian Dwellings: An Analysis of the Defect Type, Causes, Risks, and Impacts
Denman, Michael, Ullah, Fahim, Qayyum, Siddra and Olatunji, Oluwole. 2024. "Post-Construction Defects in Multi-Unit Australian Dwellings: An Analysis of the Defect Type, Causes, Risks, and Impacts." Buildings. 14 (1). https://doi.org/10.3390/buildings14010231
Key drivers of value amongst multicultural teams in construction projects
Olatunji, Oluwole Alfred and Osaghae, Ephraim. 2024. "Key drivers of value amongst multicultural teams in construction projects." International Journal of Construction Project Management. 24 (14), pp. 1581-1588. https://doi.org/10.1080/15623599.2023.2221059
The determinants of job satisfaction amongst specific migrant construction workers
Rotimi, Funmilayo Ebu, Rotimi, James Olabode Bamidele, Silva, C.W. Chathurani, Olatunji, Oluwole Alfred and Ramanayaka, Chamil Erik D.. 2023. "The determinants of job satisfaction amongst specific migrant construction workers." Built Environment Project and Asset Management. 13 (5), pp. 738-755. https://doi.org/10.1108/BEPAM-06-2022-0078
Client attributes that motivate contractors' bid decision
Olatunji, Oluwole Alfred and Ramanayaka, Chamil Erik D.. 2023. "Client attributes that motivate contractors' bid decision." Built Environment Project and Asset Management. 13 (6), pp. 799-812. https://doi.org/10.1108/BEPAM-11-2022-0181
Design-led solution for curbing crime: the case study of a major entertainment precinct in Perth, Western Australia
Jonescu, Emil E., Olatunji, Oluwole A. and Foo, Jason. 2023. "Design-led solution for curbing crime: the case study of a major entertainment precinct in Perth, Western Australia." Journal of Urban Design. 28 (1), pp. 66-94. https://doi.org/10.1080/13574809.2022.2081139
Project Management for Supplier Organisations: Harmonising the Project Owner to Supplier Relationship by Adrian Taggart
Olatunji, Oluwole. 2017. "Project Management for Supplier Organisations: Harmonising the Project Owner to Supplier Relationship by Adrian Taggart." Proceedings of the institution of Civil Engineers: Management, Procurement and Law. 170 (1), pp. 44-44. https://doi.org/10.1680/jmapl.16.00038
Analysis of contractors’ administrative characteristics in bid decision factors
Olatunji, Oluwole Alfred, Ramanayaka, Chamil Dilhan Erik, Rotimi, Funmilayo Ebun and Rotimi, James Olabode Bamidele. 2023. "Analysis of contractors’ administrative characteristics in bid decision factors." Engineering, Construction and Architectural Management. 30 (6), pp. 2420-2435. https://doi.org/10.1108/ECAM-12-2021-1063
Treatment Penetration and Correlates of Diagnostic Parameters among Hepatitis B Seropositive individuals in Ondo State, Nigeria
Odimayo, M. S., Alabi, B. Y., Adebimpe, W. O., Nwadioha, S. I., Olatunji, O. A. and Ogedengbe, B. O.. 2022. "Treatment Penetration and Correlates of Diagnostic Parameters among Hepatitis B Seropositive individuals in Ondo State, Nigeria." Western Journal of Medical and Biomedical Sciences. 3 (1), pp. 107-113. https://doi.org/10.5281/zenodo.5907250
Motivating immersive BIM uptake through user attitude: analysis of initial solution using design science approach
Ramanayaka, Chamil Dilhan Erik, Olatunji, Oluwole Alfred and Weerasuriya, Asiri U.. 2022. "Motivating immersive BIM uptake through user attitude: analysis of initial solution using design science approach." Built Environment Project and Asset Management. 12 (4), pp. 630-648. https://doi.org/10.1108/BEPAM-10-2021-0126
Critical success factors of strategy-led planning of high-profile projects
Ramanayaka, Chamil D. Erik, Olatunji, Oluwole Alfred and Rotimi, James Olabode. 2023. "Critical success factors of strategy-led planning of high-profile projects." The International Journal of Construction Management. 23 (1), pp. 75-88. https://doi.org/10.1080/15623599.2020.1849973
Multidisciplinary Perspectives of Micro Human Efforts in Post-Disaster Recovery
Subasinghe, Chamila, Sutrisna, Monty and Olatunji, Oluwole. 2021. "Multidisciplinary Perspectives of Micro Human Efforts in Post-Disaster Recovery." International Journal of Mass Emergencies and Disasters. 39 (1), pp. 1-10. https://doi.org/10.1177/028072702103900101
Editorial
Olatunji, Oluwole Alfred. 2018. "Editorial." Proceedings of the institution of Civil Engineers: Management, Procurement and Law. 171 (6), pp. 235-237. https://doi.org/10.1680/jmapl.2018.171.6.235
Managing Reality (third edition) by B. Mitchell and B. Trebes
Olatunji, Oluwole Alfred, Hammad, Ahmed, Rafel, Jeff and Martin, Monica. 2018. "Managing Reality (third edition) by B. Mitchell and B. Trebes." Proceedings of the institution of Civil Engineers: Management, Procurement and Law. 172 (1), pp. 40-41. https://doi.org/10.1680/jmapl.18.00017
Scholarship of BIM and construction law: myths, realities and future directions
Olatunji, Oluwole Alfred and Akanmu, Abiola. 2021. "Scholarship of BIM and construction law: myths, realities and future directions." Hosseini, M. Reza, Khosrowshahi, Farzad, Aibinu, Ajibade A. and Abrishami, Sepehr (ed.) BIM Teaching and Learning Handbook: Implementation for Students and Educators. United Kingdom. Taylor & Francis.
Integrating health and safety into labour-only procurement system: Opportunities, barriers and strategies
Umeokafor, Nnedinma, Windapo, Abimbola and Olatunji, Oluwole. 2020. "Integrating health and safety into labour-only procurement system: Opportunities, barriers and strategies." Manu, Patrick, Emuze, Fidelis, Saurin, Tarcisio Abreu and Hadikusumo, Bonaventura H. W. (ed.) Construction Health and Safety in Developing Countries. London, United Kingdom. Routledge. pp. 140-151
Ad hoc and post hoc analysis of contractors’ safety risks during procurement in Nigeria
Olatunji, Oluwole, Windapo, Abimbola and Umeokafor, Nnedinma. 2019. "Ad hoc and post hoc analysis of contractors’ safety risks during procurement in Nigeria." Manu, Patrick, Emuze, Fidelis, Saurin, Tarcisio Abreu and Hadikusumo, Bonaventura H. W. (ed.) Construction Health and Safety in Developing Countries. London, United Kingdom. Routledge. pp. 128-139
Innovation in the globalised world: educating future building professionals
Cooper-Cooke, Barry, Sutrisna, Monty and Olatunji, Oluwole. 2020. "Innovation in the globalised world: educating future building professionals." Construction Economics and Building. 20 (3), pp. 56-61. https://doi.org/10.5130/AJCEB.v20i3.7410
Due process and contractor selection for public works in Nigeria
Olatunji, Oluwole. 2008. "Due process and contractor selection for public works in Nigeria." Lizarralde, Gonzalo, Davidson, Colin, Pukteris, Andrea and de Blois, Michel (ed.) CIB W92, CIB TG63 and CIB W107 World congress on Building Abroad: Procurement of Construction and Reconstruction Projects in the International Context (2008). Montreal, Canada 23 - 25 Oct 2008 Montreal.
Modelling Outcomes of Collaboration in Building Information Modelling Through Gaming Theory Lenses
Olatunji, Oluwole A., Sher, Willy D. and Gu, Ning. 2010. "Modelling Outcomes of Collaboration in Building Information Modelling Through Gaming Theory Lenses." Wallis, Ian, Bilan, Lesya, Smith, Mike and Kazi, Abdul Samad (ed.) Industrialised, Integrated, Intelligent sustainable Construction: I3CON Handbook 2. Great Britain. I3CON & BSRIA. pp. 91-108
Collaboration in building information modelling: an application of gaming theory
Olatunji, Oluwole Alfred, Sher, Willy David and Gu, Ning. 2010. "Collaboration in building information modelling: an application of gaming theory." 6th International Conference on Innovation in Architecture, Engineering and Construction (AEC 2010). Pennsylvania, United States 09 - 11 Jun 2010 United kingdom.
Exploring the Performance of Australian Construction Industry in a Recent Global Recession
Olatunji, Oluwole Alfred. 2011. "Exploring the Performance of Australian Construction Industry in a Recent Global Recession." Journal of Construction Engineering and Project Management. 1 (3), pp. 1-8. https://doi.org/10.6106/JCEPM.2011.1.3.001
Building Information Modelling and Intellectual Propertization: A Revolutionary Nirvana or a Disillusionment?
Olatunji, Oluwole. 2014. "Building Information Modelling and Intellectual Propertization: A Revolutionary Nirvana or a Disillusionment?" Construction Technology and the Law: The Proceedings of the Third Society of Construction Law of Australia Conference. Society of Construction Law. pp. 77-85
Building Cost Planning for the Design Team, 3rd ed.
Smith, Jim, Jaggar, David, Love, Peter and Olatunji, Oluwole. 2016. Building Cost Planning for the Design Team, 3rd ed. London, United Kingdom. Routledge.
A preliminary review on the legal implications of BIM and model ownership
Olatunji, Oluwole. 2011. "A preliminary review on the legal implications of BIM and model ownership." Journal of Information Technology in Construction. 16, pp. 687-696.
Understanding the landscape of overruns in transport infrastructure projects
Love, Peter E. D., Smith, Jim, Simpson, Ian, Regan, Michael and Olatunji, Oluwole. 2015. "Understanding the landscape of overruns in transport infrastructure projects." Environment and Planning B: Planning and Design. 42 (3), pp. 490-509. https://doi.org/10.1068/b130102p
BIM-FM and consequential loss: how consequential can design models be?
Olatunji, Oluwole Alfred and Akanmu, Abiola. 2015. "BIM-FM and consequential loss: how consequential can design models be?" Built Environment Project and Asset Management. 5 (3), pp. 304-317. https://doi.org/10.1108/BEPAM-03-2014-0021
Public-Private Partnership Initiative in Nigeria and Its Dispute Resolution Mechanism: An Appraisal
Adekilekun, M. T., Olatunji, O. A., Gan, C. C. and Akanbi, M. M.. 2013. "Public-Private Partnership Initiative in Nigeria and Its Dispute Resolution Mechanism: An Appraisal." Journal of Malaysian and Comparative Law. 40 (1), pp. 67-86.
A comparative analysis of tender sums and final costs of public construction and supply projects in Nigeria
Olatunji, Oluwole Alfred. 2008. "A comparative analysis of tender sums and final costs of public construction and supply projects in Nigeria." Journal of Financial Management of Property and Construction. 13 (1), pp. 60-79. https://doi.org/10.1108/13664380810882084
The impact of oil price regimes on construction cost in Nigeria
Olatunji, Oluwole Alfred. 2010. "The impact of oil price regimes on construction cost in Nigeria." Construction Management and Economics. 28 (7), pp. 747-759. https://doi.org/10.1080/01446191003725162
Building Information Modeling and Quantity Surveying Practice
Olatunji, O. A., Sher, W. and Gu, N.. 2010. "Building Information Modeling and Quantity Surveying Practice." Emirates Journal of Engineering Research. 15 (1), pp. 67-70.
Modelling the costs of corporate implementation of building information modelling
Olatunji, Oluwole Alfred. 2011. "Modelling the costs of corporate implementation of building information modelling." Journal of Financial Management of Property and Construction. 16 (3), pp. 211-231. https://doi.org/10.1108/13664381111179206
Modelling organizations' structural adjustment to BIM adoption: a pilot study on estimating organizations
Olatunji, Oluwole Alfred. 2011. "Modelling organizations' structural adjustment to BIM adoption: a pilot study on estimating organizations." Journal of Information Technology in Construction. 16, pp. 653-668.
Views on building information modelling, procurement and contract management
Olatunji, Oluwole Alfred. 2014. "Views on building information modelling, procurement and contract management." Proceedings of the institution of Civil Engineers: Management, Procurement and Law. 167 (3), pp. 117-126. https://doi.org/10.1680/mpal.13.00011
Perspectives on Modelling BIM-enabled Estimating Practices
Olatunji, Oluwole Alfred and Sher, Willy. 2014. "Perspectives on Modelling BIM-enabled Estimating Practices." Australasian Journal of Construction Economics and Building. 14 (4), pp. 32-53. https://doi.org/10.5130/ajceb.v14i4.4102
A benefits realization management building information modeling framework for asset owners
Love, Peter E. D., Matthews, Jane, Simpson, Ian, Hill, Andrew and Olatunji, Oluwole A.. 2014. "A benefits realization management building information modeling framework for asset owners." Automation in Construction. 37, pp. 1-10. https://doi.org/10.1016/j.autcon.2013.09.007
Real time progress management: Re-engineering processes for cloud-based BIM in construction
Matthews, Jane, Love, Peter E. D., Heinemann, Sam, Chandler, Robert, Rumsey, Chris and Olatunji, Oluwole. 2015. "Real time progress management: Re-engineering processes for cloud-based BIM in construction." Automation in Construction. 58, pp. 38-47. https://doi.org/10.1016/j.autcon.2015.07.004
Estimating in geometric 3D CAD
Olatunji, Oluwole Alfred and Sher, Willy. 2015. "Estimating in geometric 3D CAD." Journal of Financial Management of Property and Construction. 20 (1), pp. 24-49. https://doi.org/10.1108/JFMPC-07-2014-0011
BIM-Based Decision Support System for Material Selection Based on Supplier Rating
Akanmu, Abiola, Asfari, Bushra and Olatunji, Oluwole. 2015. "BIM-Based Decision Support System for Material Selection Based on Supplier Rating." Buildings. 5 (4), pp. 1321-1345. https://doi.org/10.3390/buildings5041321
Auto-generated site layout: an integrated approach to real-time sensing of temporary facilities in infrastructure projects
Akanmu, Abiola, Olatunji, Oluwole, Love, Peter E. D., Nguyen, Duy and Matthews, Jane. 2015. "Auto-generated site layout: an integrated approach to real-time sensing of temporary facilities in infrastructure projects." Structure and Infrastructure Engineering: maintenance, management, life-cycle design and performance. 12 (10), pp. 1243-1255. https://doi.org/10.1080/15732479.2015.1110601
Constructing Dispute Scenarios in Building Information Modeling
Olatunji, Oluwole Alfred. 2016. "Constructing Dispute Scenarios in Building Information Modeling." Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. 8 (1), pp. 1-8.
Rurality, Nigeria's massification policy on access to basic education and turnover causations amongst teachers
Olatunji, Oluwole Alfred and Ajayi, Stephen Oluwatoyin. 2017. "Rurality, Nigeria's massification policy on access to basic education and turnover causations amongst teachers." Australian and International Journal of Rural Education. 26 (3), pp. 3-17.
Determining Overpricing in Brazilian Infrastructure Projects: A Forensic Approach
Signor, Regis, Love, Peter E. D. and Olatunji, Oluwole. 2016. "Determining Overpricing in Brazilian Infrastructure Projects: A Forensic Approach." Journal of Construction Engineering and Management. 142 (9), pp. 1-5. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001156
Blending ‘Fair Dinkum’ into Group Assessment of Construction Students
Olatunji, Oluwole Alfred. 2016. "Blending ‘Fair Dinkum’ into Group Assessment of Construction Students." International Journal of Construction Education and Research. 12 (4), pp. 270-284. https://doi.org/10.1080/15578771.2016.1200167
A probabilistic method for forensic cost estimating of infrastructure projects
Signor, Regis, Love, Peter E. D., Olatunji, Oluwole, Marchiori, Fernanda F. and Gripp, William G.. 2016. "A probabilistic method for forensic cost estimating of infrastructure projects." Applied Mathematical Modelling: simulation and computation for engineering and environmental systems. 40 (21-22), pp. 9197-9211. https://doi.org/10.1016/j.apm.2016.05.025
Demographic analysis of turnover intentions amongst Nigerian high school teachers
Ajayi, Stephen Oluwatoyin and Olatunji, Oluwole Alfred. 2017. "Demographic analysis of turnover intentions amongst Nigerian high school teachers." Australian and International Journal of Rural Education. 27 (1), pp. 62-87.
Chaos Theory: Implications for Cost Overrun Research in Hydrocarbon Megaprojects
Olaniran, O. J., Love, P. E. D., Edwards, D. J., Olatunji, O. and Matthews, J.. 2017. "Chaos Theory: Implications for Cost Overrun Research in Hydrocarbon Megaprojects." Journal of Construction Engineering and Management. 143 (2), pp. 1-8. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001227
Bid or no-bid decision factors of indigenous contractors in Nigeria
Olatunji, Oluwole Alfred, Aje, Olaniyi Isaac and Makanjuola, Sina. 2017. "Bid or no-bid decision factors of indigenous contractors in Nigeria." Engineering, Construction and Architectural Management. 24 (3), pp. 378-392. https://doi.org/10.1108/ECAM-01-2016-0029
Collusive bidding in Brazilian infrastructure projects
Signor, Regis, Love, Peter E. D., Olatunji, Oluwole, Vallim, Joao J. C. B and Raupp, Alexandre B.. 2017. "Collusive bidding in Brazilian infrastructure projects." Proceedings of the Institution of Civil Engineers: Forensic Engineering. 170 (3), pp. 113-123. https://doi.org/10.1680/jfoen.17.00013
Causations of failure in megaprojects: A case study of the Ajaokuta Steel Plant project
Olatunji, Oluwole Alfred. 2018. "Causations of failure in megaprojects: A case study of the Ajaokuta Steel Plant project." Frontiers of Engineering Management. 5 (3), pp. 334-346. https://doi.org/10.15302/J-FEM-2018011
Causal relationship between material price fluctuation and project’s outturn costs
Olatunji, Oluwole Alfred, Orundami, Adenike Omolabake and Ogundare, Oluwatomi. 2018. "Causal relationship between material price fluctuation and project’s outturn costs." Built Environment Project and Asset Management. 8 (4), pp. 358-371. https://doi.org/10.1108/BEPAM-12-2017-0119
Promoting student commitment to BIM in construction education
Olatunji, Oluwole Alfred. 2019. "Promoting student commitment to BIM in construction education." Engineering, Construction and Architectural Management. 26 (7), pp. 1240-1260. https://doi.org/10.1108/ECAM-04-2018-0173
It is not collusion unless you get caught: the case of ‘Operation Car Wash’ and unearthing of a Cartel
Signor, Regis, Love, Peter E. D., Vallim, Joao Jose B., Raupp, Alexandre B. and Olatunji, Oluwole. 2019. "It is not collusion unless you get caught: the case of ‘Operation Car Wash’ and unearthing of a Cartel." Journal of Antitrust Enforcement. 7 (2), pp. 177-202. https://doi.org/10.1093/jaenfo/jnz009
Critical overrun causations in marine projects
Karami, Hamidreza and Olatunji, Oluwole Alfred. 2020. "Critical overrun causations in marine projects." Engineering, Construction and Architectural Management. 27 (7), pp. 1579-1594. https://doi.org/10.1108/ECAM-09-2019-0477
Musculoskeletal disorders within the carpentry trade: analysis of timber flooring subtasks
Akanmu, Abiola, Olayiwola, Johnson and Olatunji, Oluwole Alfred. 2020. "Musculoskeletal disorders within the carpentry trade: analysis of timber flooring subtasks." Engineering, Construction and Architectural Management. 27 (9), pp. 2577-2590. https://doi.org/10.1108/ECAM-08-2019-0402
Automated checking of building component accessibility for maintenance
Akanmu, Abiola A., Olayiwola, Johnson and Olatunji, Oluwole Alfred. 2020. "Automated checking of building component accessibility for maintenance." Automation in Construction. 114, pp. 1-10. https://doi.org/10.1016/j.autcon.2020.103196
Discussion of 'State of Practice of Building Information Modeling in the Electrical Construction Industry' by Awad S. Hanna, Michael Yeutter, and Diane G. Aoun
Love, P. E. D., Zhou, J., Matthews, J., Sing, C. - P., Olatunji, O. and Carey, B.. 2016. "Discussion of 'State of Practice of Building Information Modeling in the Electrical Construction Industry' by Awad S. Hanna, Michael Yeutter, and Diane G. Aoun." Journal of Construction Engineering and Management. 142 (3), pp. 1-3. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001069
Impact and Remedy of Legal Uncertainties in Building Information Modeling
Alwash, Adam, Love, Peter E. D. and Olatunji, Oluwole. 2017. "Impact and Remedy of Legal Uncertainties in Building Information Modeling." Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. 9 (3), pp. 1-7. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000219
Overrun causations under advance payment regimes
Aje, Olaniyi Isaac, Olatunji, Oluwole Alfred and Olalusi, Olanrewaju Augustine. 2017. "Overrun causations under advance payment regimes." Built Environment Project and Asset Management. 7 (1), pp. 86-98. https://doi.org/10.1108/BEPAM-06-2015-0028
Sustainable public-private partnerships: Balancing the multi-actor ecosystem and societal requirements
Leviakangas, Pekka, Ye, Yanbing and Olatunji, Oluwole Alfred. 2018. "Sustainable public-private partnerships: Balancing the multi-actor ecosystem and societal requirements." Frontiers of Engineering Management. 5 (3), pp. 347-356. https://doi.org/10.15302/J-FEM-2018020
Turnover Causation Amongst High School Teachers in Nigeria
Ajayi, Stephen O. and Olatunji, Oluwole A.. 2019. "Turnover Causation Amongst High School Teachers in Nigeria." Africa Education Review. 16 (2), pp. 1-15. https://doi.org/10.1080/18146627.2016.1224602
Key value engineering protocols in marine projects
Karami, Hamidreza and Olatunji, Oluwole Alfred. 2020. "Key value engineering protocols in marine projects." Proceedings of the institution of Civil Engineers: Management, Procurement and Law. 173 (1), pp. 21-31. https://doi.org/10.1680/jmapl.19.00010
Building information modelling (BIM) penetration in quantity surveying (QS) practice
Olatunji, Oluwole Alfred, Lee, Jane Jia Suen, Chong, Heap -Yih and Akanmu, Abiola Abosede. 2021. "Building information modelling (BIM) penetration in quantity surveying (QS) practice." Built Environment Project and Asset Management. 11 (5), pp. 888-902. https://doi.org/10.1108/BEPAM-08-2020-0140
Briefing: A framework for integrating health, safety and well-being into labour-only procurement
Umeokafor, Nnedinma, Windapo, Abimbola and Olatunji, Oluwole. 2021. "Briefing: A framework for integrating health, safety and well-being into labour-only procurement." Proceedings of the institution of Civil Engineers: Management, Procurement and Law. 174 (4), pp. 141-144. https://doi.org/10.1680/jmapl.20.00010
Migrant construction workers’ demography and job satisfaction: a New Zealand study
Rotimi, James Olabode Bamidele, Ramanayaka, Chamil Dilhan Erik, Olatunji, Oluwole Alfred and Rotimi, Funmilayo Ebun. 2021. "Migrant construction workers’ demography and job satisfaction: a New Zealand study." Engineering, Construction and Architectural Management. https://doi.org/10.1108/ECAM-05-2021-0457
Evaluation of postural-assist exoskeleton for manual material handling
Ogunseiju, Omobolanle, Olayiwola, Johnson, Akanmu, Abiola and Olatunji, Oluwole. 2022. "Evaluation of postural-assist exoskeleton for manual material handling." Engineering, Construction and Architectural Management. 29 (3), pp. 1358-1375. https://doi.org/10.1108/ECAM-07-2020-0491
Detection of Collusive Tenders in Infrastructure Projects: Learning from Operation Car Wash
Signor, Regis, Love, Peter E. D., Belarmino, Alexanders T. N. and Olatunji, Oluwole Alfred. 2020. "Detection of Collusive Tenders in Infrastructure Projects: Learning from Operation Car Wash." Journal of Construction Engineering and Management. 146 (1), pp. 1-10. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001737
Understanding how policy settings affect developer decisions
Rowle, Steven, Leishman, Chris, Olatunji, Oluwole, Zuo, Jian and Crowe, Adam. 2022. Understanding how policy settings affect developer decisions. Australia. Australian Housing and Urban Research Institute (AHURI). https://doi.org/10.18408/ahuri8124201
Editorial
Olatunji, Oluwole. 2015. "Editorial." Proceedings of the institution of Civil Engineers: Management, Procurement and Law. 168 (5), pp. 203-204. https://doi.org/10.1680/jmapl.2015.168.5.203