Method for calculating schedule delay considering weather conditions
Paper
Paper/Presentation Title | Method for calculating schedule delay considering weather conditions |
---|---|
Presentation Type | Paper |
Authors | Thorpe, David (Author) and Karan, Ebrahim Parvaresh (Author) |
Editors | Dainty, Andrew |
Journal or Proceedings Title | Proceedings of the 24th Annual Conference of the Association of Researchers in Construction Management (ARCOM 2008) |
ERA Conference ID | 42470 |
Journal Citation | 2, pp. 809-818 |
Number of Pages | 10 |
Year | 2008 |
Place of Publication | Cardiff, Wales |
ISBN | 9780955239014 |
Web Address (URL) of Paper | http://www.arcom.ac.uk/publications/procs/ar2008-809-818_Thorpe_and_Karan.pdf |
Conference/Event | 24th Annual Conference of the Association of Researchers in Construction Management (ARCOM 2008) |
Association of Researchers in Construction Management Annual Conference | |
Event Details | Association of Researchers in Construction Management Annual Conference ARCOM ARCOM Conference Rank A A A A A A A A |
Event Details | 24th Annual Conference of the Association of Researchers in Construction Management (ARCOM 2008) Parent Association of Researchers in Construction Management Annual Conference Event Date 01 to end of 03 Sep 2008 Event Location Cardiff, Wales |
Abstract | As construction work is affected by weather events such as snow, cold temperature, humidity, and rainfall, conditions. Thus, to calculate acceptable delay duration, a reasonable method, suitable for practitioners, for predicting schedule delays caused by weather conditions is necessary. Therefore, in this study, we propose a method for calculating construction schedule delays where weather conditions are taken into consideration. This methodology combines weather information, the expected delay to particular types of construction as a result of altered weather conditions, and scheduling data, to determine the project duration and make it possible to reduce delays with the help of changes in commencement time of the project or modified scheduling. The objectives of the paper are twofold. The first objective is to provide a prediction of the potential delay as a result of weather conditions. The second objective is to help planners to make decisions making regarding the optimum construction approach to meet the project schedule given expected weather conditions. |
Keywords | construction; delays; schedule; project management; weather |
ANZSRC Field of Research 2020 | 370108. Meteorology |
490108. Operations research | |
330202. Building construction management and project planning | |
Public Notes | This publication is copyright. It may be reproduced in whole or in part for the purposes of study, research, or review, but is subject to the inclusion of an acknowledgment of the source |
Byline Affiliations | Department of Agricultural, Civil and Environmental Engineering |
Amirkabir University of Technology, Iran |